What a Camden handover list looks like
Room by room, and one item that is not about paint at all.
In short: The shape of a practical completion list from an Oran Park job four kilometres away.
Painting, recorded room by room
Common areas, master bedroom, bathrooms, ensuites, toilets, the powder room and the ground floor were each recorded separately. That is not padding; it is how a builder's trades are actually dispatched.
The stairs
Balustrades left unpainted, and masking tape still attached to them at practical completion. Tape on a handrail is evidence the painter never came back to that element.
Glazing and joinery
Mirrors marked, a window frame damaged, a laundry trough marked, a splashback recorded. Small items, cheap now, awkward after settlement.
The building items
Caulking outstanding at wall, eave, door and window joints. Pipe penetrations through the external wall unsealed. Grading still required around the house. These are envelope items, not finish.
The one that matters most
The termite management notice not installed. It is required under AS 3660 and it is the only record of what protects the house from termites.
Written by the Owner Inspections team from inspections carried out in Gledswood Hills. Licensed building practitioners, NSW Fair Trading licence 366177C.